Location: Bern
Canton: Bern
Project name: Geothermal energy storage at Forsthaus Bern
Project owner: Energie Wasser Bern (ewb)
Project type: Geothermal energy storage for seasonal heat storage as part of the municipal district heating
supply
Status of work:
-
October 2017: Submission of the application for approval of the drilling for the exploration of the
geothermal storage facility to the authorities
-
October 2017: Public presentation of the project
-
October 2017: Positive decision on funding as a pilot and demonstration facility by the Swiss Federal
Office of Energy
-
May 2018: Positive decision on funding for the project as part of the international research project
HEATSTORE
-
October 2018: Drilling permit obtained
-
May 2019: Positive decision on funding for the exploration of the geothermal reservoir at the Forsthaus
Bern pilot project under CO2 legislation
-
2020-2021: Construction of the drilling site
-
April 2022: Drilling contract awarded to PR Marriott Drilling Limited, along with other service
contracts.
Next steps:
-
October 2022: Start of drilling work